Formal Public Consultation for Application Ref No: FS006859 took place between Wednesday 11th March and Thursday 4th June 2020.
- Submissions were received by the DoHLGH from both the public and statutory bodies and sent to DP Energy for response.
- DP Energy returned a ‘Response to Submissions’ document to the DoHLGH to address matters raised in these submissions.
- We are currently awaiting the decision regarding our Foreshore Licence Application.
As a result of the feedback we received from the public during phase one consultation we will not progress investigations within the eastern-most ‘leg’ (leading to the coast off Helvick Head).
Submission call advertised in the local press
Formal Public Consultation for Application Ref no. FS007404 took place between Thursday 21st October until 19th November 2021. Supporting documentation can be found here.
A separate Foreshore Licence Application was submitted to the DoHLGH in July 2021 for an alternative investigation area between Youghal and Ballymacoda.
This broadly follows similar routing to the Celtic Interconnector.